Lot QHH-HD5 of the Qinhuai River (Shiiu Lake in Lishui -Pengfu in Jiangning section ) Waterway Rehabilitation Project

Section QHH-HD5 - Initial Phase

Qinhuai River Waterway Rehabilitation Project

Project Brief

The Qinhuai River is part of the Wushen Line, one of the "Four Horizontal Routes" in the "Two Vertical and Four Horizontal" trunk waterway network outlined in the Jiangsu Provincial Trunk Waterway Network Plan, classified as a Grade lV waterway.

Our company won the bid for Section QHH-HD5 on July 3, 2017. The main construction work included waterway regulation and reinforced concrete works for the waterway, covering a cumulative length of 3.004km within the section.

Key Construction Quantities

  • Earthwork: 1,814,137 m³
  • Geomembrane: 377,165 m²
  • Concrete lining for waterway: 91,255 m³

Project Overview

The QHH-HD5 section represents the initial phase of the comprehensive Qinhuai River rehabilitation initiative. This section serves as a critical link in the regional water transport network, connecting key industrial areas and facilitating the movement of goods throughout the region.

The successful completion of this section has significantly improved navigation conditions, reduced sedimentation issues, and enhanced the overall ecological health of the waterway. The project employed advanced engineering techniques to ensure long-term sustainability and minimal environmental impact.

Construction Achievements

  • Successfully completed 3.004km of waterway rehabilitation
  • Implemented state-of-the-art erosion control systems
  • Constructed durable concrete lining with enhanced durability
  • Improved waterway dimensions to meet Grade IV navigation standards
  • Integrated ecological restoration measures along the waterway banks